Generator cable sizing and voltage drop: how to choose the conductor


A generator cable is chosen twice: once for the current it has to carry, and once for the voltage it is allowed to lose. The current comes from the set rating, not from the site load, and the loss is checked against 5 % of the supply voltage. Whichever check asks for the larger conductor wins, and on a generator the current almost always speaks first.

Full load current is the first number, and it comes from the kVA

The current per phase is not a property of the site. It is a property of the set, and it is fixed the moment the rating and the voltage are fixed. For a three phase set it is the apparent power in kVA multiplied by 1000, divided by the square root of three times the line voltage.

At 400 V the working figure is 1.44 A per kVA. A 500 kVA set delivers 721.7 A per phase whether the building behind it is fully loaded or sitting idle, because the cable has to be safe at the rating the machine can produce, not at the load someone expects to connect. How the apparent power in kVA is separated from the real power in kW, and why the cable is sized on the former, is set out in kVA vs kW.

Full load current per phase against the set rating, at 400 V and at 415 V, using I = kVA x 1000 / (1.732 x V). The values are the planning currents used throughout this page.
Set rating Current at 400 V Current at 415 V Amps per kVA at 400 V
100 kVA 144.3 A 139.1 A 1.44
150 kVA 216.5 A 208.7 A 1.44
200 kVA 288.7 A 278.2 A 1.44
250 kVA 360.8 A 347.8 A 1.44
320 kVA 461.9 A 445.2 A 1.44
400 kVA 577.4 A 556.5 A 1.44
500 kVA 721.7 A 695.6 A 1.44
630 kVA 909.3 A 876.5 A 1.44
800 kVA 1154.7 A 1113.0 A 1.44
1000 kVA 1443.4 A 1391.2 A 1.44

Two things follow from this table, and both of them matter more than the table itself. The first is that a set ordered at 415 V carries about 3.6 % less current than the same set at 400 V, so a cable chosen against the wrong voltage column is either oversized or quietly undersized. The second is that the current rises in step with the kVA, so a decision to move from 400 kVA to 500 kVA is a decision to re-size the cable, the breaker and the terminal lugs as well. How the two voltages and the two phase arrangements are specified is set out in generator voltage and phases.

A cable is chosen twice: capacity first, voltage drop second

The two checks are not alternatives. They are done in order, and the second one is done on the size the first one produced.

The capacity check asks whether the conductor can carry the current without exceeding its temperature limit, once the installation has been accounted for. It starts from a base figure published by the cable manufacturer and then applies a correction for the ambient temperature and for how many circuits share the route. That corrected figure has to be at least the full load current. Where the load list behind that current comes from, and how diversity and derating shape the set rating, is covered in how to size a diesel generator.

The voltage drop check then asks how much voltage the chosen route loses along the way, and whether that loss is acceptable at the far end. It is not a safety limit. It is a performance limit, and it is checked last because it is usually the check that can be satisfied by adding a second run rather than by changing the whole design.

Planning current-carrying capacities for four-core copper XLPE cable, clipped direct, three loaded conductors, 30 °C ambient, before any correction. The figures move with the installation method, so they are a starting point, not a selection.
Conductor Capacity before correction Typical use on a 400 V set
95 mm² 282 A Glanded tails on 150 to 200 kVA, short routes
120 mm² 328 A Single run on the smaller end of 200 kVA
150 mm² 379 A Single run at 200 kVA, or one of two runs at 400 kVA
185 mm² 434 A The common single run at 250 to 300 kVA
240 mm² 514 A Single run at 300 kVA, or one of two runs at 500 kVA
300 mm² 593 A Practical limit of a single copper run; above this, parallel the runs

The important line in that table is the last one. Copper stops being practical somewhere around 300 mm², and it stops for handling reasons as much as electrical ones: larger conductors are stiff, the bending radius grows, and terminating them needs more room in the cabinet than most genset enclosures have. Above roughly 600 A the answer on a generator installation is almost always more than one run per phase.

The two factors that quietly reduce the capacity you paid for

A cable selected straight from the capacity table is a cable selected for a laboratory. Two corrections are applied on top of the base figure, and in the Gulf the first of them is not a formality.

The first is ambient temperature. Conductor capacity is quoted at 30 °C, and a generator room, a plant room or a rooftop enclosure in the Gulf is routinely at 45 to 50 °C. The correction for that is a reduction of roughly one fifth of the quoted figure, and it has to be applied before the cable is compared with the load. The same conditions derate the machine as well as the cable, which is set out in diesel generators in hot and humid climates.

The second is grouping. Two or more loaded circuits running together in the same tray, duct or cable trench share the heat, and each of them loses capacity. Three circuits together lose about 30 %.

Ambient temperature correction for XLPE insulated cable, conductor rated 90 °C, in air. The base rating is quoted at 30 °C.
Ambient temperature Correction factor What it means on a 500 kVA set
25 °C 1.03 No reduction
30 °C 1.00 Reference condition
35 °C 0.96 A 4 % reduction before anything else is counted
40 °C 0.91 721.7 A becomes 793 A of required base capacity
45 °C 0.87 Shaded plant room in summer
50 °C 0.82 Enclosed generator room or rooftop in the Gulf; 880 A required
55 °C 0.76 Unventilated enclosure near a roof slab
60 °C 0.71 At this point the machine itself is also derated
Grouping correction for circuits bunched together in air. It is applied on top of the temperature correction, not instead of it.
Loaded circuits sharing the route Correction factor Combined with 50 °C
1 1.00 0.82
2 0.80 0.66
3 0.70 0.57
4 0.65 0.53
5 0.60 0.49
6 0.57 0.47

Read the two tables together and the arithmetic stops being academic. A 500 kVA set needs 721.7 A. In a Gulf plant room at 50 °C with three circuits in the same tray, the combined factor is 0.82 x 0.70, or 0.57, and the cable has to be able to carry 1257 A before correction before it can carry 721.7 A after it. That is not a marginal difference. It is the difference between two runs per phase and four.

Voltage drop: the calculation, and the numbers it needs

Voltage drop on a three phase circuit is calculated from the conductor’s resistance and reactance, the current, the length of the run, and the power factor of the load. In the form used for planning it is written as millivolts per amp per meter, so that the drop falls out directly from the current and the distance.

The number the drop is measured against is the supply voltage, and the allowance is written as a percentage of it. Five percent is the conventional total from the alternator terminals to the furthest load. On a 400 V set that is 20 V, and if the run feeds a final distribution board rather than a single machine, the last section is usually held to half of that.

Three phase voltage drop for copper conductors at 0.8 power factor, in millivolts per amp per meter. Drop in volts is the figure multiplied by the current in amps and the length in meters, divided by 1000. For parallel runs, divide by the number of runs.
Conductor mV per A per m Drop at 721.7 A over 50 m Drop at 721.7 A over 250 m
16 mm² 2.40 86.6 V Not a practical route
25 mm² 1.50 54.1 V Not a practical route
35 mm² 1.10 39.7 V Not a practical route
50 mm² 0.81 29.2 V Not a practical route
70 mm² 0.57 20.6 V Not a practical route
95 mm² 0.43 15.5 V 77.6 V
120 mm² 0.35 12.6 V 63.1 V
150 mm² 0.29 10.5 V 52.3 V
185 mm² 0.25 9.0 V 45.1 V
240 mm² 0.21 7.6 V 37.9 V
300 mm² 0.18 6.5 V 32.5 V
400 mm² 0.15 5.4 V 27.1 V

The 20 V allowance sounds generous against a single run, and it is. A single 185 mm² run loses 9.0 V over 50 m, which is 2.3 % and comfortably inside it. The same run over 250 m loses 45.1 V, which is 11 %, and no amount of re-checking will change that. Distance is the variable that turns voltage drop from a formality into the binding constraint, and it is the one figure that is most often missing from the enquiry.

Worked example: 500 kVA at 400 V, 50 m, in a Gulf plant room

Take a 500 kVA set at 400 V, 721.7 A per phase, a route of 50 m from the alternator terminals to the main distribution board, three circuits sharing the tray, and a plant room at 50 °C. The combined correction factor is 0.57, so the conductor has to be good for 1257 A before correction. The table below works the common options through both checks.

Six ways to make the same connection, each checked for capacity after correction and for voltage drop at 50 m. The capacity column is the base figure with 0.57 applied; the set draws 721.7 A.
Runs per phase Base capacity After 0.57 Drop at 50 m Result
2 x 150 mm² 758 A 435 A 5.23 V, 1.31 % Capacity short by 287 A
2 x 185 mm² 868 A 498 A 4.51 V, 1.13 % Capacity short by 224 A
3 x 120 mm² 984 A 565 A 4.21 V, 1.05 % Capacity short by 157 A
2 x 240 mm² 1028 A 590 A 3.79 V, 0.95 % Capacity short by 132 A
3 x 185 mm² 1302 A 747 A 3.01 V, 0.75 % Passes both checks
4 x 120 mm² 1312 A 753 A 3.16 V, 0.79 % Passes both checks

Every one of those six options passes the voltage drop check with room to spare. Only two of them pass the capacity check. That is the single most useful thing to understand about cable sizing on a generator: at ordinary distances the drop is not what decides the size, and the answer is driven by the number of runs, which is driven by the corrections.

Now stretch the same route to 300 m and the picture turns over. Three runs of 185 mm² lose 18.0 V at 300 m, which is 4.5 % and still inside the 20 V allowance but with almost nothing left for the final circuit downstream. At 350 m the same installation fails on drop, and the fix is not a bigger conductor that no longer exists but a change of route, a step-up and step-down arrangement, or a set installed closer to the load. The length of the run is a design decision, not a detail to be settled after the cable is ordered. Where the far end will not tolerate a 5 % dip, as on a data centre UPS distribution, the same calculation is done against a much tighter figure, for the reasons given in data centre backup power.

The neutral and the protective conductor on a generator supply

Two conductors in the same cable are not sized the same way as the phases, and both are decided by the installation rather than by the set.

The neutral carries the imbalance between the three phases, and on a linear, well balanced load it carries less current than a phase conductor, which is why a reduced neutral is sometimes offered. On a generator supply it is rarely the right choice. Modern loads are not linear: variable speed drives, UPS systems, LED lighting and switch mode power supplies all draw third harmonic current, and third harmonic currents in the three phases add in the neutral instead of cancelling. A neutral reduced to half the phase conductor can be badly overloaded on a supply that looks perfectly balanced on a clamp meter. Keep the neutral at full size unless the load is known to be linear and balanced, and remember that the same question decides whether the transfer switch needs four poles, which is covered in ATS vs AMF.

The protective conductor is sized from the phase conductor rather than from the current, using the relationship set out in the wiring rules for the cross-section involved. Its job is different from the job of the phases: it has to carry fault current long enough for the breaker to operate, and it has to keep the touch voltage low while it does. On a generator supply it deserves more attention than it usually gets, because the source cannot deliver the fault current a transformer can, which is the subject of the next section.

Breaker sizing on a generator is not transformer practice

The circuit breaker on a generator is asked to do two jobs that pull in opposite directions, and a breaker selected the way the same current would be selected on a mains supply does neither of them well.

The first job is to protect the cable, which sets a ceiling on the rating: the breaker must operate before the conductor overheats. The second is to protect the alternator, which is a much more delicate machine than a transformer of the same rating. An alternator’s fault current is limited by its own reactance, and it typically delivers only about three times its rated current into a short circuit, sustained for around ten seconds. A transformer of the same rating delivers fifteen to twenty times. That single difference changes how the protection has to be set.

Typical breaker selection against set rating at 400 V. The breaker is set at or just above the alternator’s rated current, which lands on the next standard rating up, and the short-time delay is set inside the alternator’s withstand.
Set rating Full load current Breaker rating Setting against full load
100 kVA 144.3 A 160 A 111 %
200 kVA 288.7 A 320 A 111 %
320 kVA 461.9 A 500 A 108 %
400 kVA 577.4 A 630 A 109 %
500 kVA 721.7 A 800 A 111 %
630 kVA 909.3 A 1000 A 110 %
800 kVA 1154.7 A 1250 A 108 %
1000 kVA 1443.4 A 1600 A 111 %

Three settings follow from that table, and they are the three that cause most of the trouble in the field.

  • The overload setting sits at or just above the alternator’s rated current, never far enough above it that the machine can be overloaded for minutes without the breaker noticing. A set is not protected by a breaker that is generous with it.
  • The short-time delay is set to ride through motor starting, which is what generator fault finding turns on when a breaker trips on a perfectly healthy installation. The delay has to be shorter than the alternator’s withstand, or the protection outlasts the machine it is protecting.
  • The instantaneous element is either set well above the starting current or disabled, because on a low fault current source it is more likely to catch a motor starting than a fault. Whether the set runs as a standby machine or as the only source changes how it is set, and the two duties are described in prime and standby power.

Where several sets run together, each one carries its own outgoing protection and the calculations are done per set, because the fault current available at any one breaker depends on how many machines are running at the instant of the fault. That is one of the reasons a paralleled installation is commissioned as a system rather than as a set of machines, as set out in generator paralleling.

Distance, parallel runs and aluminium

Three variables change the answer more often than any other, and all three are usually settled by the installer after the set has been ordered.

Distance is the one that has no substitute. Voltage drop is proportional to length, so doubling the route doubles the loss, and the only ways to answer it are a larger conductor, more runs in parallel, a shorter route, or a different voltage. Because the current per phase falls as the voltage rises, a site that can accept a higher distribution voltage gets a thinner cable for the same power, which is a design conversation worth having before the alternator is ordered rather than after.

Parallel runs are the normal answer above roughly 600 A, and they are not quite the simple division they look like. Two runs per phase each carry half the current, so the drop halves and the capacity doubles, but each run has to be the same size and the same length, must be run together and terminated in the same way, and must be grouped in the derating calculation because they heat each other. A 2 x 185 mm² pair is not the same installation as a single 370 mm² conductor that does not exist.

Aluminium is a legitimate choice and is common on longer runs where weight and cost matter. It needs roughly 1.6 times the cross-section of copper for the same voltage drop and about 1.3 times for the same current, so the cable is physically larger for the same job. The terminations need more care, with the correct bi-metallic interfaces and a compound where the standard calls for one, and the compression lugs are a different part number. Where the run is short and the enclosure is tight, copper usually still wins. On an export project the standards that fix the cable type, the terminations and the test evidence are collected in generator export certification.

Mistakes that cost money

  • Sizing the cable on the load rather than on the set. The measured load may be 60 % of the rating on the day the cable is ordered, and the set will still deliver its nameplate current the first time a chiller starts with everything else running.
  • Skipping the temperature correction. A selection made at 30 °C in a plant room that runs at 50 °C is oversubscribed by about a fifth, and the failure appears months later as a warm cable rather than as a tripped breaker.
  • Forgetting that parallel runs count as grouped circuits. The derating is applied to each run, and the second run also reduces the capacity of the first.
  • Setting the breaker to the cable and not to the alternator. A breaker sized to protect a 300 mm² cable is a breaker that will happily let a smaller alternator be overloaded.
  • Leaving the run length out of the enquiry. It is the single figure that decides whether voltage drop matters at all, and it is the one most often missing from a request that otherwise lists everything.
  • Ordering the cable before the voltage is confirmed. A 400 V selection fitted to a 415 V set is wrong in the safe direction and expensive, and the reverse is neither.

Questions we are asked

How do I calculate the current a generator has to supply?

Divide the apparent power in kVA by the line voltage, then multiply by 1000 and divide by 1.732. A 500 kVA set at 400 V gives 500 x 1000 / (1.732 x 400), which is 721.7 A per phase. At 415 V the same set gives 695.6 A. The figure is the same whether the site is fully loaded or not, because it is the current the machine can produce rather than the current the load draws.

What is an acceptable voltage drop on a generator supply?

Five percent of the supply voltage from the alternator terminals to the furthest point of use, which is 20 V on a 400 V system. Where the run ends at a distribution board and the final circuits run beyond it, the submain is usually held to about half of that so the final circuit has something left. These are performance limits rather than safety limits, and they exist because motors draw more current and run hotter at reduced voltage.

Does the generator cable have to be bigger than the mains cable for the same load?

Usually, yes, and for two reasons. The cable is sized on the set’s rated current rather than on the site’s diversified load, so it is sized on a larger number. And the set is often further from the load than the mains intake was, so the same current is being carried over a longer distance. Both effects push the conductor up.

Can I use aluminium cable for a generator installation?

Yes, and it is a reasonable choice on long runs. Aluminium needs about 1.6 times the cross-section of copper for the same voltage drop and about 1.3 times for the same current, so the cable is larger for the same duty. The terminations need the correct bi-metallic interfaces and the right compound, and the lugs are a different part. On short runs inside an enclosure copper is usually simpler.

Why does my breaker trip when a large motor starts?

Almost always because the instantaneous element is set low enough to see the motor starting current as a fault. A motor draws several times its running current while it accelerates, and on a generator the voltage dips at the same moment, which lengthens the start and the current surge. The answer is a short-time delay set inside the alternator’s withstand, not a larger breaker, because a larger breaker no longer protects the machine.

Should the cable be sized on the alternator rating or on the breaker rating?

On whichever is the larger of the two, which in practice means the two have to be coordinated rather than chosen independently. The cable must be protected by the breaker, so the breaker’s setting is the ceiling; the cable must also carry the set’s full load current, so the alternator rating is the floor. A design that satisfies one and not the other is a design that will be changed later.

Can the neutral be smaller than the phase conductors?

It can be, and on a known linear balanced load it often is. On a generator supply feeding drives, UPS systems and electronic lighting it should not be, because third harmonic currents from the three phases add in the neutral rather than cancelling, and a reduced neutral can end up carrying more than its rating on a supply that measures as balanced. Keeping the neutral at full size also keeps the four-pole transfer switch decision open.

What do you need from me to size the cable?

Four figures: the set rating in kVA, the supply voltage and phase arrangement, the distance from the alternator terminals to the load, and the installation: in air, in a tray, in a duct or buried, with the ambient temperature and the number of circuits sharing the route. With those we will come back with the current per phase, the number of runs, the conductor size, the drop at that length and the breaker setting that goes with it.

Send the current, the distance and the installation

Tell us the set rating in kVA, the supply voltage, the distance from the alternator terminals to the load, and how the cable will be installed. We will come back with the current per phase, the number of runs and conductor size, the voltage drop at that length and the breaker setting that coordinates with the alternator.

Request a quote WhatsApp the sales desk

Written and maintained by the KVA Grid sales engineering desk. The currents on this page are calculated as kVA multiplied by 1000 and divided by 1.732 times the line voltage, rounded to 0.1 A. The voltage drop figures are three phase planning values for copper conductors at 0.8 power factor, applied as the figure in millivolts per amp per meter multiplied by the current in amps and the length in meters, divided by 1000 and by the number of parallel runs. Capacity figures are planning values for four-core copper XLPE cable, clipped direct, three loaded conductors at 30 °C, before the temperature and grouping corrections shown. All of them move with the installation method, the cable manufacturer and the site conditions, so they are planning figures rather than a cable schedule, and they are not a substitute for the project design. This page explains how a conductor and its protection are selected on a generator supply and is not a quotation or advice on any specific project. Reviewed 7 October 2026.