Application

Diesel Generators for Data Centers

A data centre generator is sized from the load steps the UPS, the chillers and the pumps present after a utility failure, and from the redundancy the hall was designed to — not from the IT load alone. In a colocation hall the rating and the number of sets follow the design.

Standby generator sets for data centres are normally quoted at 500 kVA and above, arranged in N+1 or 2N groups, with paralleling controls, automatic transfer at each level of the distribution and on-site fuel for the autonomy the site declares to its clients.

Request a quote
Chat on WhatsApp

Requirements

What a data centre specification has to state

The rows below are the items that change the machine. Two halls of the same IT capacity can need very different generators, depending on the answers.

Typical data centre generator requirements. The facility design and the local code govern.
Item Typical requirement Why it changes the set
Redundancy N+1 as a minimum for concurrently maintainable operation; 2N for fault-tolerant halls Fixes how many sets, and whether paralleling control is required
Duty rating Standby (ISO 8528-1 ESP, or DCP where the duty is declared as data centre power) ESP and PRP are different numbers from the same hardware; in regions with a weak grid the duty becomes closer to prime power
Load acceptance The declared step-load curve for the set, against the largest step the hall can present Chillers and large UPS rectifiers are the steps that decide the rating
Transfer time UPS carries the IT load; the generator must be at voltage and frequency before the UPS battery is exhausted, and before mechanical cooling restarts Sets the allowable start sequence, and whether a black-start sequence is needed
Autonomy Commonly 12-24 h of on-site fuel at full load; longer where fuel delivery is unreliable Drives bulk storage, day tanks, transfer pumps and bunding
Ambient 45-50 °C design ambient with the radiator sized for it A set quoted at 40 °C is derated above it, and a roof-level radiator sees the highest temperature on site
Noise Typically 65-75 dB(A) at the nearest receptor, not at the set Decides the enclosure and whether a wall or a roof screen is needed
Harmonics The alternator sized for non-linear loads from UPS and drive equipment, with a stated sub-transient reactance Harmonic current heats the alternator beyond its kW rating
Paralleling and control Load sharing, reverse power protection, synchronising, and reporting to the building management system Determines the control panel scope and the interface to the hall monitoring
Testing Witnessed load bank test at commissioning, and periodic testing afterwards Rated load data has to be demonstrated, not assumed

Configurations

Configurations we quote most often

Each rating below links to the power range page, which carries the specification envelope, the fuel figures and the options for that class.

Common data centre arrangements by hall size. The number of sets follows the redundancy target, not the load.
Rating per set Typical arrangement Fits Range page
500 kVA / 400 kW Two sets, N+1, one bus Small hall or an edge site with a single mechanical plant 500 kVA
800 kVA / 640 kW Two or three sets, N+1 Mid-size hall, split UPS and mechanical buses 800 kVA
1000 kVA / 800 kW Two groups of two, 2N Fault-tolerant hall where each path must stand alone 1000 kVA
2000 kVA / 1600 kW Multiple sets in parallel, N+1 or 2N Large campus or a hall with central chilled water plant 2000 kVA

Reference configuration

A worked example

This is an illustrative configuration, not a delivered project. It shows how the requirement table above turns into a specification. Replace the figures with your own load list before pricing.

Example: a two-path hall of about 800 kW of critical IT load with central chilled water plant.
Parameter Example value
Critical IT load 800 kW, delivered through two UPS systems
Mechanical load Two chillers at 300 kW each plus pumps and fans
Redundancy 2N on the generator bus, so two independent sets per path
Rating selected Four sets at 1000 kVA / 800 kW, standby rating, paralleled within each path
Largest load step One chiller started with soft start, about 300 kW running, plus UPS recharge
Autonomy 24 h at full load on bulk storage with a day tank and transfer pump
Enclosure Containerised sets at roof level, or open sets in a ventilated generator hall
Control Paralleling panels, load sharing, reverse power protection, BMS reporting
Testing Load bank test at commissioning with the mechanical plant running, then periodic testing

Questions

Questions we are asked about data centre sets

What is the difference between N+1 and 2N for a generator plant?

N+1 means one set more than the load needs, so a single set can be taken out for service without interrupting the hall. 2N means two complete independent supplies, each able to carry the whole load on its own, which is what fault tolerance requires. 2N needs twice the sets of N, doubles the switchgear and needs two separate fuel or cabling paths to mean anything.

How fast does a data centre generator have to start?

The generator does not have to beat the IT load, because the UPS battery does that. What it has to beat is the UPS battery autonomy and the cooling plant restart window. Common design targets are the generator at voltage and frequency within about 10-15 seconds, ready to accept the mechanical plant load shortly afterwards. Where the whole load is on battery, the actual constraint is how long the batteries last, which is usually measured in minutes.

How do you size a generator for a chilled water plant?

Start from the largest single step, not the total. A chiller with a soft starter or a variable speed drive presents a much smaller starting step than one started direct on line, and starting the machines in sequence rather than together often lets a smaller set carry the same plant. The declared load acceptance curve for the set, at the site ambient, is the document that proves whether the step is acceptable.

Should data centre sets be containerised or installed in a hall?

Both are common. Containerised sets at roof or yard level save building volume and are easy to replace, but they need clear air paths and they count against the site’s roof loading. A ventilated generator hall gives better access for major maintenance and better acoustic control, at the cost of building area. The mechanical and electrical design of the site usually decides it.

How much fuel autonomy is normal?

Twelve to twenty-four hours at full load is the common range, and 24 h is the figure most often written into client commitments. The volume that implies is large: at 0.24-0.27 litres per kWh delivered, 400 kW of load needs roughly 2 300-2 600 L for 24 h, per running set. That is why the bulk tank, the bunding and the transfer pump are part of the generator scope rather than a site afterthought.

Limitations

Where a diesel set is not the right answer in a data hall

In a data centre the set is normally part of the topology rather than an option, and it is justified by the load steps the hall has to accept and by the redundancy the space is sold with. These are the cases where we tell a client the answer is somewhere else.

Cases in a data hall where the generator is not the answer, and what is.
Case Why the set is not the answer What to specify instead
A hall sold with a single incoming supply and no load step to accept The redundancy the customer is paying for is in the supply and the topology, and a set cannot create it Agree the topology with the customer first, and place the plant where the design says it goes
The essential load is the IT load only, and the ride-through already covers the changeover A generator adds fuel storage, testing and a maintenance regime for a load the batteries are already carrying Size the battery autonomy for the changeover, and keep the set for the mechanical plant where the outage runs long
A hall in a building that cannot store fuel or reach a flue route No fuel storage and no exhaust route means no set, whatever the load list says A plant position outside the building, or a supply agreement that covers the essential load
Chiller and pump plant that cannot be restarted in a controlled sequence The set is sized by the step the mechanical plant presents, and a step it cannot take is a design problem rather than a generator problem Agree a staged restart with the mechanical designer before the set is sized

Specifying standby plant for a data hall?

Send the critical load, the largest step, the redundancy target and the fuel autonomy. Those four answers fix the number of sets and the rating of each one.

Request a quote

Scroll to Top
WhatsApp