A diesel generator is not a stock item, so its lead time is a production slot plus the build rather than a shelf-to-doorstep figure, and it is quoted together with the delivery term. EXW, FOB and CIF decide who arranges and pays for the freight, and both the date and the term are written into the quotation before the order.
What a generator lead time is actually made of
Lead time is the period between the order being placed and the set being ready to leave the works, and it is not one process. It is a queue followed by a build. The queue is the production slot, the window reserved for this order in the build programme. The build is everything from the approved drawings to the factory test and the packing. Reading a single figure such as “delivery in six weeks” without knowing which of the two is being quoted is how a project ends up waiting at the gate.
| Stage | What happens | What it depends on |
|---|---|---|
| Production slot | The order takes its place in the build programme | How full the programme is, and when the advance payment clears |
| Drawing approval | Enclosure, container or trailer drawings are issued and returned approved | How quickly the drawing is approved; changes after approval restart this stage |
| Long-lead components | The engine and the alternator are ordered against the configuration | The rating, the voltage and frequency, and the make specified |
| Enclosure and tank | The canopy or the container shell and the base tank are built | Whether it is a catalogue enclosure or a custom one |
| Assembly | Engine, alternator, radiator, panel and switchgear are mounted and wired | The controls and the accessories on the order |
| Factory test | The set is run, and load tested where a load bank is specified | The test slot, and whether the buyer attends |
| Packing and inland transport | The set is drained, packed and moved to the port on the chosen term | The delivery term, and the sailing the forwarder has booked |
Only the first stage is a queue in the ordinary sense, where the answer is simply how many orders are ahead. The other six are work, and work responds to decisions. A drawing approved in one pass, a voltage decided before the alternator is ordered and a load bank test booked with the slot all come off the calendar; a configuration changed in the middle of the build adds to it.
What changes the lead time
The rating rarely decides the lead time on its own; the configuration around it does. A catalogue canopy set built from standard drawings moves through the works in the shortest time, and every departure from the catalogue adds a step that has to be engineered and approved. Those steps are what the date on a quotation is really estimating.
| Build option | What it adds | Why |
|---|---|---|
| Catalogue canopy set | The base case | Standard drawings, standard enclosure and standard base tank |
| Custom acoustic canopy | Typically 2-6 weeks longer than a catalogue canopy | The enclosure drawings are usually approved before the shell is built |
| Containerised set | A container shell build, plus the CSC plate and the corner fittings | The box is a certified freight container and is inspected as one |
| Trailer-mounted set | A chassis, axle and braking build under the set | The trailer is a separate structure with its own approval |
| Paralleled sets | Two or more builds, plus the synchronising switchgear and the site settings | The sets and the paralleling panel are commissioned together |
| Non-standard voltage, or 60 Hz | The alternative alternator carries its own availability | The winding and the excitation are built for the rating |
| Set with ATS or AMF | The panel is built and wired as part of the package | The transfer logic has to be tested against the set |
The acoustic canopy figure is the one that can be put on a page, and it is the one on our silent diesel generator page: a custom silent canopy runs about 2 to 6 weeks longer than a catalogue canopy, because the drawings are approved before the shell is built. Everything else in the table is a stage rather than a fixed number of days, and for a particular project the honest answer is the one the quotation carries.
Delivery lead time and parts lead time are two different questions, and only the first is about the arrival of the set. How fast a fuel injector or a water pump arrives in year five is a separate comparison, and it is one of the points set out in Cummins against Perkins.
The production slot, and how the advance payment holds it
A slot is a reservation in the build programme, and it is held against the advance payment. On our terms the schedule is 30 % of the contract value as an advance payment after the contract is signed, with production scheduled when the payment is received, and the remaining 70 % due before shipment. That sequence, with the delivery terms and the warranty period, is set out on the payment and delivery terms page, and it is what turns a date on a quotation into a date on a calendar.
The advance payment is an advance against the contract value rather than a forfeitable deposit, and the reason it is tied to the slot is practical: engines, alternators and container shells are ordered against a confirmed build, and a slot released late cannot always be refilled. If a project is still waiting on internal approval, say so at the enquiry stage. A slot can be held for a stated period, and it is cheaper to agree that period in writing than to re-book the slot later.
Four lines are enough to hold a date and to price the move, and they can all be given before the rating is finally settled:
- The destination port, and the inland address if the set is going past the port.
- The delivery term you intend to use, EXW, FOB or CIF.
- The rating and the configuration: enclosure, base tank, controls and any paralleling.
- The date the set is wanted on site, and whether a witness test is wanted at the works.
EXW, FOB and CIF in plain terms
The three delivery terms we quote divide the same journey in three different places, and the division is fixed by the term rather than by goodwill. The term is chosen by the buyer and named in the quotation together with the place or the port, and it decides who books the freight, who pays for it and who carries the risk at each stage.
| Term | We are responsible for | The buyer is responsible for |
|---|---|---|
| EXW – ex works | Making the set ready at our works and loading it onto the vehicle the buyer sends | Arranging the freight forwarder and the vehicle, and all cost and risk from collection onwards, including export clearance, shipping and onward transport |
| FOB – free on board | Moving the set to the agreed port, completing export clearance and loading it on board | The sea freight and the risk during the sea leg |
| CIF – cost, insurance and freight | The freight to the agreed port of destination and the marine insurance for the voyage | Import clearance at the destination port and the charges for collecting the goods |
Two consequences follow from that table. Under an EXW term the buyer owns the export clearance, which surprises buyers who are used to FOB and who have no customs agent at our end. Under a CIF term the buyer still owns the import clearance, so a quotation that looks complete on the equipment side can stop at the destination port until an importer of record is in place. The terms themselves, with the payment schedule and the warranty period, are on the payment, delivery and warranty page; this page explains what sits behind them.
What the freight quote depends on
Freight is not a single rate per set, and two identical machines going to two different ports do not cost the same to move. The quotation prices the journey on the term chosen, and the forwarder needs the following before any figure means anything.
- The destination port. The named port decides the sailing, the transit time and the rate.
- The inland leg. A set that continues past the port needs a truck, and a long or heavy load needs a route survey and sometimes an escort.
- The size and the mass of the package. Not the rating but the overall dimensions and the total mass, because those decide whether the set goes in a container, on a flat rack or as breakbulk.
- The number of packages. A base tank, an ATS panel, an exhaust silencer or a set of spares travelling separately changes the count and the handling.
- The fuel in the tank. A tank drained to the minimum the carrier allows travels as machinery; a full tank can turn the set into a dangerous goods consignment.
- The term. Under EXW the buyer prices the whole move, under FOB we price it to the port, and under CIF we price it to the destination port and add the marine insurance.
Because the freight follows the destination rather than the machine, an equipment price and a delivered price are not comparable figures, and a quotation should always state the term and the named place. The same logic runs through the cost of ownership, where freight, duty and installation sit alongside the fuel and the maintenance in diesel generator total cost of ownership.
Packing a set for sea freight
Sea freight is the hardest journey a set makes, because the load lasts for weeks and the machine sits on a deck, on a flat rack or in a hold rather than on a concrete plinth. Packing is therefore decided by the form of the set and by how it will be lifted, and three things travel with every shipment: the fuel, the lifting points and the paperwork.
Fuel first. A set shipped with a full tank is a different consignment from the same set drained, and the difference is visible at the quay. The usual approach is to drain the tank to the minimum the carrier allows, so that the machine stays ordinary freight rather than a dangerous goods class. That point is set out on the containerized generator applications page, and it applies to every form, not only to a set inside a container.
| Form of set | How it usually travels | What to watch |
|---|---|---|
| Open frame | On its own skid, often shrink wrapped | The skid and the radiator are exposed, so the marked lifting points matter |
| Canopy set | On its skid, crated where the route is rough | The canopy is a weather cover rather than a packing case, and a sling can dent it |
| Containerised set | In its own certified container | The CSC plate, the corner fittings and the box mass are part of the shipment |
| Trailer-mounted set | Rolled or lifted as a trailer | The axles, the brakes and the tyres travel with the set and need their own tie-down |
Lifting is second. A set is lifted on the components designed for it: the corner castings on a container, the marked points on a skid, or a spreader beam over four points on a larger machine. What is not a lifting point is a canopy panel, a radiator frame or a base tank flange, and more sets are damaged in the yard than at sea. The three forms compare on noise and cost in silent against open frame, which is the other half of the packing decision.
Container loading: what fits and what does not
Whether a set goes into a container is answered by the envelope, not by the rating. Three numbers decide it: the internal length of the box, the door opening and the maximum gross mass. The internal length is the one that catches people out, because a 20 ft container is 6 058 mm long on the outside and about 5 898 mm inside, and a set on a skid needs clearance at both ends on top of that.
| Check | What it decides | The figure |
|---|---|---|
| Internal length | Whether the set and its skid fit along the floor with clearance at both ends | About 5 898 mm in a 20 ft box and about 12 032 mm in a 40 ft high cube |
| Door opening | Whether the set passes the door frame even when it would fit the floor | About 2 340 x 2 280 mm on a 20 ft box |
| Maximum gross mass | Whether the loaded box stays inside the rating on its plate | 30 480 kg, or 36 000 kg on a box built to the 2016 revision |
| Package mass | Whether the mass limit or the length limit binds first | The set, the base tank, the skid and any loose items weighed together |
Those checks produce two answers that matter. A set that fits the envelope goes into a standard box and travels as freight, which is the cheapest way to move it. A set that exceeds the envelope in height, width or mass does not go in at all: it goes on a flat rack or as breakbulk on a general cargo ship, and both are priced differently and booked further ahead. There is no rule of thumb that gives the number of sets of a given rating that fit a 40 ft box, because the answer depends on the overall length of each set, the skid, the base tank and the total mass. The formats and the typical ratings are on the containerized diesel generators page, and on a large machine the logistics change the whole project: a 2000 kVA set needs heavier lifting and a road survey at each end as well as a longer delivery lead time.
The documents that travel with the set
Documents are as much a part of a shipment as the packing, and one missing paper stops a set at the port however well it was built. The list below is the transport set, which is a different list from the engineering package and the conformity package; those, with the certificate of origin, the commercial invoice and the packing list in their place, are collected in generator export certification.
| Document | Who uses it | When it is needed |
|---|---|---|
| Commercial invoice | The buyer and the customs authority at destination | With the shipment, for import clearance |
| Packing list | The forwarder, the buyer and customs at destination | It ties each package, its dimensions and its mass to the shipment |
| Certificate of origin | The importer of record and customs at destination | Where the destination needs proof of origin or a trade agreement applies |
| Bill of lading or sea waybill | The carrier, the buyer and the bank | It is the transport contract and, on a bill of lading, the document of title |
| Marine insurance certificate | The buyer, on a CIF term | With the shipping documents, to support a claim on the voyage |
| Factory test report | The buyer’s maintenance records | With the set, and with the acceptance step before shipment |
Two of those documents are produced after the set is built and are issued against the shipment as booked, which is why the sequence matters. The factory test report comes from the pre-acceptance test, and the bill of lading is issued only once the goods are on board. A change to the destination port or the consignee after the documents are issued means they are reissued, and that is a delay no amount of production planning can recover. What the factory test itself covers, the readings the report carries and what a site acceptance test adds after installation are set out in factory test and site acceptance.
Mistakes that cost time, and what prevents them
The delays we see rarely start at the factory, and most of them are visible well in advance.
- The destination changes after the quotation. A new port or a new inland leg changes the freight, and on a CIF term the insurance with it. Agree the destination before the shipment is booked and it costs nothing.
- The drawings are approved late. A custom enclosure cannot be built until its drawing is approved, and every day of approval is a day of the build. Return the drawing marks in one pass where you can.
- The clearance documents are treated as an afterthought. The importer of record, the certificate of origin and any destination marking are the buyer’s side of the border, and they cannot be improvised on arrival.
- Only the equipment price is compared. An equipment price and a delivered price are not the same figure, and the gap is the freight and the insurance. Compare quotations on the same term, with the named port.
- The slot is assumed rather than written. A slot is held against the advance payment, and an unwritten expectation is not a reservation. Confirm the payment and the slot in writing.
- The tank is shipped full. It is the quickest way to turn a routine shipment into a dangerous goods booking and a delay at the terminal.
- A built set is expected to be returnable. These are built to order, so a cancelled set cannot go back on a shelf. What protects the order is the factory acceptance test and the warranty instead.
The order is protected from the other side by the sequence itself: a factory pre-acceptance test before shipment, a balance instalment that falls due only before shipment, and a warranty of 12 months from the works date or 1000 running hours, whichever comes first. Where the set will run in parallel with others, the switchgear adds its own commissioning, which is the point at which the delivery schedule meets generator paralleling. Where a short-term duty is being weighed instead, the trade-off is set out in rental against buying, and where the duty rating itself is still open, it changes the availability as well as the capacity, a point covered in prime and standby power.
Questions about lead time, packing and shipping
How long is the lead time for a diesel generator?
There is no single figure, because it is a production slot plus a build. A catalogue canopy set moves through the works in the shortest time, and a custom acoustic canopy runs about 2 to 6 weeks longer than a catalogue canopy, because the enclosure drawing is approved before the shell is built. The engine and the alternator are bought against the configuration, and a container or a trailer adds its own build on top. The date on the quotation is the one estimated for that configuration. The rating question itself is a separate exercise, worked through in how to size a diesel generator.
What is the difference between EXW, FOB and CIF?
They divide the same journey in different places. Under EXW the set is made ready at our works and loaded onto the buyer’s vehicle, and the buyer arranges everything from there. Under FOB we move the set to the agreed port, complete the export clearance and load it on board, and the buyer pays the sea freight and carries the risk during the sea leg. Under CIF we add the freight to the destination port and the marine insurance for the voyage, while the buyer still clears the import and collects the goods.
Is the sea freight included in the price?
It depends on the term, which is why the term is named on every quotation. A quotation on an EXW term prices the set at the works, an FOB quotation prices it to the port of loading, and a CIF quotation prices it to the named port of destination and includes the marine insurance. Ask for the term and the named place on any quotation, and the freight can be read separately from the equipment.
Can the destination port be changed after the order?
Yes if it is done before the shipment is booked, and it changes the freight cost and, on a CIF term, the insurance. After the shipping documents have been issued, a change to the port or the consignee means the documents are reissued, which delays the shipment. The earlier the destination is known, the cheaper the change, which is why it belongs at the enquiry stage.
How many generator sets fit in a container?
It is a calculation rather than a rule of thumb. A 20 ft box gives about 5 898 mm of internal length and a 40 ft high cube about 12 032 mm, and the set has to fit with clearance on its skid and stay within the maximum gross mass of the box, 30 480 kg or 36 000 kg on a box built to the 2016 revision. A set that exceeds the envelope in height, width or mass goes on a flat rack or as breakbulk instead, and both are booked further ahead.
Is the set shipped with fuel in the tank?
No. The tank is drained to the minimum the carrier allows, so that the machine travels as ordinary freight rather than as a dangerous goods consignment. A full tank changes the consignment class and the paperwork with it, and it delays the set at the terminal.
What packing does a set travel in?
It follows the form of the set. An open frame set travels on its own skid, often shrink wrapped; a canopy set travels on its skid and is crated where the route is rough; a containerised set travels in its own certified container; and a trailer-mounted set is rolled or lifted as a trailer, with the axles and the brakes tied down. In every case the lift is made on the designed points, and the dimensions, the mass and the lifting points go to the forwarder before the booking is made.
What happens if the set fails the factory test?
It is repaired or re-tested before shipment, and the balance instalment is not due until the set is accepted. The factory pre-acceptance test is the step we recommend, either in person at the works or remotely from high-resolution photographs and video, and it is the point at which a problem is cheapest to put right. Anything that appears later is handled as a warranty claim, with the warranty running for 12 months from the works date or 1000 running hours, whichever comes first.
Send the destination, not only the rating
Give us the rating and the configuration, the destination port and the inland address, and the delivery term you intend to use. The reply carries the lead time for that build, the packing and the lifting data, and the freight on the term you have chosen.
Written and maintained by the KVA Grid sales engineering desk. The commercial terms behind this page, the 30 % advance payment, the 70 % balance before shipment, the EXW, FOB and CIF split and the warranty of 12 months or 1000 running hours, follow the payment, delivery and warranty page, and this page explains the process behind them rather than restating them. The container figures are the ISO 668 dimensions used on the containerized generator applications page and are confirmed against the box actually used. Freight rates, sailing schedules and port charges are quoted for the specific shipment and are not published, and nothing on this page is a quotation for a particular project. Reviewed 9 October 2026.