Size a hospital set from the essential-load block, not from the building’s connected load. A 250 kW essential block at 0.80 power factor is 313 kVA, and 388 kVA while a 30 kW compressor starts on it. That points at a 500 kVA set — or at two of them with a bus tie if the essential supply is never allowed to wait for maintenance.
Split the load into three groups before you size anything
A hospital is not sized on one load figure, because the standby supply is not meant to carry the whole building. The load is split first, and the split is what decides the rating, the number of sets and the changeover arrangement.
| Group | What sits in it | What the generator does |
|---|---|---|
| Life safety | Fire pump and pressurisation, smoke extract, escape lighting and signage, firefighting lift | Carried first, on every set in the scheme |
| Critical | Operating theatres, ICU and NICU, recovery, laboratories, blood bank and pharmacy cold storage, medical air and vacuum, nurse call, IT and security, and the ventilation serving those rooms | Carried, and restored within seconds of the transfer |
| Equipment | Passenger lifts, kitchen, laundry, general air conditioning, non-clinical socket outlets | Shed on transfer and restored once the essential block is stable |
The single-line diagram has to show that split, because the load-shedding scheme is part of the machine’s rating. The same electrical installation described on the hospital generator page is normally quoted as two sets with automatic transfer rather than one large machine.
What a 40- to 60-bed hospital actually draws
Once the groups are agreed, the load list is written item by item. The figures below are an indicative first pass for a hospital of that size, at 400/230 V, 50 Hz; the real numbers come from the equipment schedule and the mechanical and electrical consultant.
| Load | Group | Running load |
|---|---|---|
| Fire pump, pressurisation and smoke extract | Life safety | 57 kW |
| Escape lighting, signage and fire alarm | Life safety | 18 kW |
| Operating theatres (2) and recovery | Critical | 40 kW |
| ICU and NICU, 6 bed spaces | Critical | 28 kW |
| Laboratories, blood bank and pharmacy cold storage | Critical | 20 kW |
| Medical air, medical vacuum and oxygen plant | Critical | 20 kW |
| Nurse call, IT, servers, security and comms | Critical | 15 kW |
| Ventilation and cooling for theatres, ICU and isolation rooms | Critical | 52 kW |
| Passenger lifts (2) | Equipment | 30 kW |
| Kitchen, laundry and general air conditioning | Equipment | 120 kW |
| Essential block: life safety plus critical | — | 250 kW |
| Whole site including the equipment group | — | 400 kW |
Two things follow from that table. The essential block is 250 kW, not the 400 kW on the incoming supply, and the largest motor on it is a 30 kW medical air compressor. The rest of the calculation is the same one used on any site:
- Essential running load at 0.80 power factor: 250 ÷ 0.8 = 313 kVA.
- Compressor starting on a soft starter, about 2.5 times its rating: 30 × 2.5 = 75 kVA of starting demand.
- Demand at the moment of the start: 313 + 75 = 388 kVA.
- Add 10 % for load growth: about 427 kVA.
427 kVA is not a standard size, so the answer is the next one up: a single 500 kVA set, or two of them with a bus tie where the essential supply must survive both a fault and a service visit. The kW to kVA step itself is worked through in how to size a diesel generator.
Starting demand decides the rating more often than the load does
A motor draws several times its full-load current while it accelerates, and its power factor during the start is poor. The set sees a short, large kVA demand and has to ride it without dropping the voltage far enough to trip contactors or stall the motor.
| Starting method | Starting current | Starting kVA, rough order |
|---|---|---|
| Direct-on-line (DOL) | 6 to 8 times full load | 6 to 8 times the motor kW |
| Star-delta | About one third of DOL | 2 to 3 times the motor kW |
| Soft starter | 2 to 3 times full load | 2 to 3 times the motor kW |
| Variable frequency drive | About 1 to 1.5 times full load | The set still sees drive harmonics, so the load is not purely resistive |
On the example above, the compressor starting direct-on-line instead of on a soft starter changes the answer twice: 30 × 6.5 = 195 kVA of starting demand, so 313 + 195 = 508 kVA, and 559 kVA with the growth allowance — a 800 kVA set in place of a 500 kVA one. A starter on one compressor is worth more than a bigger machine, and it is the first question worth asking about the mechanical schedule.
Restoration time is a question for the batteries, not for the set
A standby set starts and takes over in seconds. Theatre lighting, life support, monitors, the IT stack and the medical air plant cannot wait even that long, so they ride on UPS or battery-backed supplies until the set is on load — the set’s job is to be carrying the block before those batteries are spent. What that means in practice: the transfer arrangement and the UPS autonomy have to be designed together, with the life-safety supply restored first and the critical branches following, and the equipment group shed rather than allowed to fight the essential block for the first seconds.
Start reliability belongs in the same paragraph. Two independent starting batteries, a coolant heater on a set that sits in a cold plant room, fuel that has been checked for water and sediment, and a monthly run under load. A standby set that is only ever started off load is the most common reason a hospital transfer fails when it is finally needed.
Fuel autonomy: size the tank from the essential block
Autonomy is a site decision, and 24 hours of on-site fuel for the essential load is a common starting point on hospital projects. At three-quarter load a diesel set burns roughly 0.20 to 0.22 litres per kWh, so a 500 kVA set running at 300 kW takes about 60 to 70 litres per hour — and 24 hours of that is 1,440 to 1,680 litres. Usable tank volume is less than the nameplate figure, so a 2,000 litre tank is the practical answer; heavy fuel users go to bulk storage with day tanks. Ask for the set’s fuel curve rather than a rule of thumb, and check how the tank is filled, vented and bunded before the plant room layout is fixed.
Conditions that change the answer
- Ambient temperature. A rating is declared at reference conditions. A set quoted for a Gulf plant room in summer is de-rated for a higher ambient, and the datasheet figure for your build is the one that counts.
- Harmonics. Scanners, LED lighting and drives draw non-linear current that heats the alternator beyond what its kW rating suggests. The alternator is de-rated for the non-linear portion — the kW total can look comfortable while the alternator is not.
- Imaging inrush. A CT or MRI draws a large kVA for a fraction of a second at the start of a scan. Where radiology is on the essential block, the alternator is sized for the inrush and the harmonic content, not for the average.
- Plant room heat and noise. A hospital plant room has to reject the set’s heat somewhere and stay below the level allowed at the nearest ward. If it cannot do either, the set moves outside, in a canopy or a container.
- Duty rating. A standby set and a prime set of the same kVA are not the same machine; the difference is explained in prime vs standby power.
When a single set is the wrong answer
One machine is not always the honest answer, and the cases where it is not are worth stating plainly:
- The essential block runs past roughly 1 MW. Two sets in parallel are then usually cheaper than one very large machine, and they leave room for the next extension without replacing the plant.
- Maintenance must never interrupt the essential supply. Two sets with a bus tie mean either one can be serviced while the other carries the block; the price of that is that each set is sized for the whole essential load, so it is 2 × 500 kVA in the example above, not 2 × 250 kVA. A pair arranged to shed the critical group and keep only life safety would be smaller, but that arrangement accepts losing theatres and ICU on the second fault, and a hospital specification usually rules it out.
- There is nowhere to put the fuel. If the autonomy required cannot be stored on site, the answer is not a smaller tank, it is a different supply arrangement.
- The plant room cannot take the set. Weight, heat rejection and the noise limit at the boundary are constraints on the room, not on the machine; when any of them fails, the set goes outside.
Questions
How do I size a generator for a hospital?
Write the load list in three groups, add up the life-safety and critical loads, convert to kVA at 0.8 power factor, then add the starting demand of the largest motor on that block. In the worked example a 250 kW essential block is 313 kVA, a 30 kW compressor on a soft starter adds 75 kVA, and 10 % growth brings it to about 427 kVA — one 500 kVA set, or two for redundancy.
How much fuel does a hospital generator need on site?
Work from the essential load, not from the tank size. 24 hours of autonomy is a common requirement; a 500 kVA set at 300 kW burns roughly 60 to 70 litres per hour, so about 1,600 litres plus the unusable volume at the bottom of the tank — a 2,000 litre tank in practice. The exact figure comes from the set’s fuel curve at the load you expect, and the tank has to be fillable and bunded in the space you have.
Can one generator supply the whole hospital?
It can be built to, but the standby supply is normally designed not to. In the example the essential block is 250 kW against 400 kW for the whole site, so the equipment group — lifts, kitchen, laundry, general air conditioning — is shed on transfer and restored after the essential block is stable. That is a decision written into the single-line diagram, and it is what keeps the machine inside a sensible size.
Do CT and MRI need their own generator?
Not always, but they need an alternator that can take the inrush and the harmonic current, and a feeder of their own. Where radiology is procured as a separate package it often gets a dedicated set for exactly that reason. If the scanners sit on the essential set, size the alternator for the scan, not for the average load of the room.
What to send for a quotation
Send the load list with the three groups marked, the starting method of the largest motor, the supply voltage and frequency, the autonomy required, and the site conditions if the plant room is already fixed. A single-line diagram or a tender document helps more than a description. With those in hand the reply carries the rating, the configuration, the tank and the lead time.
Send the essential-load list and get a rating back
We answer with the kVA, the number of sets, the enclosure, the tank and the transfer arrangement — in writing, usually the same working day.
Written and maintained by the KVA Grid sales engineering desk. Figures are for 400/230 V, 50 Hz, three-phase sets unless stated, and every set is quoted against its own datasheet. Load figures are indicative for a 40- to 60-bed hospital and are not a substitute for the project load schedule. Reviewed 30 September 2026.